BRAINERD LAKE DAM PROJECT UPDATE
September 8, 2014
The last section of the wall is complete. The concrete cantilever cap and walk is complete. Sediment removal is complete. The roadway excavation on the east side is complete. The granite curb has been delivered. |
|