				| BRAINERD LAKE DAM PROJECT UPDATE 
 January 29, 2014
 
 The concrete curb wall was poured and the fill area between the sheet piling and curb wall was poured. The spillway area was excavated for the proposed foundation. Concrete construction barriers were installed on the east side of the road.
 |  |