Author Message
fyi
PostPosted: Thu, Jan 30 2014, 10:09 am EST    Post subject: BRAINERD LAKE DAM PROJECT UPDATE

BRAINERD LAKE DAM PROJECT UPDATE

January 29, 2014

The concrete curb wall was poured and the fill area between the sheet piling and curb wall was poured. The spillway area was excavated for the proposed foundation. Concrete construction barriers were installed on the east side of the road.