Posted: Fri, Sep 12 2014, 6:25 am EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
anon;36-1-2q17 wrote: | The word on the street is it will now cost one million bucks to dredge the lake and possibly as much as another million to ship the soil to Pa. if they can't dump it in Cranbury. The last time they dredged they built the mountain in the park where the kids play!----Anybody ever hear of the term Historic Pesticides?Here we go on another spending spree with a bunch of consultant expenses . I'm sure some committee members have some contacts that really need the work! |
To be clear, you'd rather we not have a lake? |
|
 |
anon;36-1-2q17 |
Posted: Fri, Sep 12 2014, 12:17 am EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
The word on the street is it will now cost one million bucks to dredge the lake and possibly as much as another million to ship the soil to Pa. if they can't dump it in Cranbury. The last time they dredged they built the mountain in the park where the kids play!----Anybody ever hear of the term Historic Pesticides?Here we go on another spending spree with a bunch of consultant expenses . I'm sure some committee members have some contacts that really need the work! |
|
 |
anon-26o4 |
Posted: Fri, Sep 5 2014, 7:56 pm EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
What about the "lake". It'll be a swamp soon if we don't manage it. What's the plan there? |
|
 |
anon-921r |
Posted: Fri, Sep 5 2014, 6:25 am EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
I have seen updates in the TC meeting notes.
What I understand.
- the project was delayed when they had found a large sink hole under the road needing repair. That this delayed the project by about one month.
- that the main work has been inside the lake where we would not see it from the road.
- walking kids to school yesterday it looks like the spillway is complete and curbs being laid.
In the TC meeting notes Dave Cook is managing the project. So if people have questions he'd be the one to contact. |
|
 |
anon-p99p |
Posted: Fri, Sep 5 2014, 6:16 am EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
It will be done when it's completed. Be glad the road is still open in both directions. |
|
 |
anon;34-2-2q17 |
Posted: Thu, Sep 4 2014, 10:12 pm EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
Can any town offical tell us when this bridge project might get done? The contractor seems to work on and off and has not met the completion date? |
|
 |
anon-s44o |
Posted: Tue, Aug 19 2014, 1:27 pm EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
Lake maintenance (or rehab) plan? Anyone know? |
|
 |
anon-p8n2 |
Posted: Wed, Aug 13 2014, 4:42 pm EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
Is there a plan for the lake itself???? It looks terrible and is getting worse every year. |
|
 |
anon-p830 |
Posted: Mon, Aug 11 2014, 12:51 pm EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
Sorry for my persistence but can we get an update on the lake itself? It's overall health and plans to maintain it? It's not looking good. Thanks again |
|
 |
anon-97on |
Posted: Thu, Aug 7 2014, 8:13 pm EDT Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE |
|
Beggars can't be choosers I guess, but it would be nice if the updates were more than a sentence. More details on the expected status of the schedule, any possible road closers, etc. |
|
 |
fyi |
Posted: Thu, Aug 7 2014, 9:46 am EDT Post subject: BRAINERD LAKE DAM PROJECT UPDATE |
|
BRAINERD LAKE DAM PROJECT UPDATE
August 6, 2014
Construction of the forms for the spillway weir continues with the installation of the sluice gate wall thimble and 42” pipe. |
|
 |