Author Message
anon-921r
PostPosted: Fri, Sep 12 2014, 6:25 am EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

anon;36-1-2q17 wrote:
The word on the street is it will now cost one million bucks to dredge the lake and possibly as much as another million to ship the soil to Pa. if they can't dump it in Cranbury. The last time they dredged they built the mountain in the park where the kids play!----Anybody ever hear of the term Historic Pesticides?Here we go on another spending spree with a bunch of consultant expenses . I'm sure some committee members have some contacts that really need the work!


To be clear, you'd rather we not have a lake?
anon;36-1-2q17
PostPosted: Fri, Sep 12 2014, 12:17 am EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

The word on the street is it will now cost one million bucks to dredge the lake and possibly as much as another million to ship the soil to Pa. if they can't dump it in Cranbury. The last time they dredged they built the mountain in the park where the kids play!----Anybody ever hear of the term Historic Pesticides?Here we go on another spending spree with a bunch of consultant expenses . I'm sure some committee members have some contacts that really need the work!
anon-26o4
PostPosted: Fri, Sep 5 2014, 7:56 pm EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

What about the "lake". It'll be a swamp soon if we don't manage it. What's the plan there?
anon-921r
PostPosted: Fri, Sep 5 2014, 6:25 am EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

I have seen updates in the TC meeting notes.

What I understand.

- the project was delayed when they had found a large sink hole under the road needing repair. That this delayed the project by about one month.

- that the main work has been inside the lake where we would not see it from the road.

- walking kids to school yesterday it looks like the spillway is complete and curbs being laid.

In the TC meeting notes Dave Cook is managing the project. So if people have questions he'd be the one to contact.
anon-p99p
PostPosted: Fri, Sep 5 2014, 6:16 am EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

It will be done when it's completed. Be glad the road is still open in both directions.
anon;34-2-2q17
PostPosted: Thu, Sep 4 2014, 10:12 pm EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

Can any town offical tell us when this bridge project might get done? The contractor seems to work on and off and has not met the completion date?
anon-s44o
PostPosted: Tue, Aug 19 2014, 1:27 pm EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

Lake maintenance (or rehab) plan? Anyone know?
anon-p8n2
PostPosted: Wed, Aug 13 2014, 4:42 pm EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

Is there a plan for the lake itself???? It looks terrible and is getting worse every year.
anon-p830
PostPosted: Mon, Aug 11 2014, 12:51 pm EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

Sorry for my persistence but can we get an update on the lake itself? It's overall health and plans to maintain it? It's not looking good. Thanks again
anon-97on
PostPosted: Thu, Aug 7 2014, 8:13 pm EDT    Post subject: Re: BRAINERD LAKE DAM PROJECT UPDATE

Beggars can't be choosers I guess, but it would be nice if the updates were more than a sentence. More details on the expected status of the schedule, any possible road closers, etc.
fyi
PostPosted: Thu, Aug 7 2014, 9:46 am EDT    Post subject: BRAINERD LAKE DAM PROJECT UPDATE

BRAINERD LAKE DAM PROJECT UPDATE

August 6, 2014

Construction of the forms for the spillway weir continues with the installation of the sluice gate wall thimble and 42” pipe.