PostPosted: Tue, Sep 9 2014, 11:18 am EDT    Post subject: BRAINERD LAKE DAM PROJECT UPDATE

BRAINERD LAKE DAM PROJECT UPDATE

September 8, 2014

The last section of the wall is complete. The concrete cantilever cap and walk is complete. Sediment removal is complete. The roadway excavation on the east side is complete. The granite curb has been delivered.