main street dam
Post new topic   Reply to topic    [http://cranbury.info] -> News | Events
View previous topic :: View next topic  
Author Message
anon-257q
Guest





PostPosted: Sun, Nov 30 2014, 12:10 am EST    Post subject: Re: main street dam Reply with quote

Can someone from the TC post the status of finishing the dam work? When will the rails, benches, etc. go in?

Thanks.
Back to top
D Cook-405s
Guest





PostPosted: Tue, Dec 2 2014, 9:07 pm EST    Post subject: Re: main street dam Reply with quote

Hello resident,
The work on the dam and bridge is nearly complete. The primary issues that are outstanding currently are the following:

1. Railing on the East and West side

2. The new Street lighting design and hardware for the over head street lighting.

3. The Bridge benches

First,the railing is a custom railing that has to be manufactured and assembled from custom made parts from multiple vendors. We are expecting the deliver of the railing by the end of this month or beginning of January.

Second is the overhead Street lighting that we have contracted with PSE&G to install. The lighting hardware is also custom and is of a historical design. Though the hardware is not unique it is not kept in inventory and has been back ordered for at least 4 weeks. We are expecting delivery at the same time as the railing however the railing must be installed first before PSE&G can put in the lighting.

Last are the benches. They are being restored and will most likely be returned to there bench pads after the railing and lights have been installed. The reason is that we don't want the benches damaged by or in the way of the trucks that will be installing the lights above the street.

Its been a 3 year project and we are down to the last few items. The Township is applying as much pressure as we can to have these last few important construction issues resolved. As soon as I get any definitive information on the above issues I will post here and let you know.

Thank you
Dave Cook
Township Committee
Back to top
Guest 4-n54o
Guest





PostPosted: Tue, Dec 2 2014, 9:20 pm EST    Post subject: Re: main street dam Reply with quote

What are the additional costs associated with these delays? How does the cost now compare to the original cost when the project was awarded?
Back to top
anon-02s3
Guest





PostPosted: Tue, Dec 2 2014, 11:02 pm EST    Post subject: Re: main street dam Reply with quote

Appreciate the update, Dave. It's coming together well.. Cannot wait to see finished product.
Back to top
anon-3q51
Guest





PostPosted: Wed, Dec 3 2014, 3:01 pm EST    Post subject: Re: main street dam Reply with quote

There are no additional costs related to the delays so it hasn't changed the original cost of the project.
Thank you
Dave Cook
Township Committee
Back to top
anon-4731
Guest





PostPosted: Thu, Dec 11 2014, 3:19 pm EST    Post subject: Re: main street dam Reply with quote

Thanks for the update
Back to top
anon-4731
Guest





PostPosted: Thu, Dec 11 2014, 3:22 pm EST    Post subject: Re: main street dam Reply with quote

Thanks for the update
Back to top
anon-6q91
Guest





PostPosted: Sat, Dec 13 2014, 6:59 pm EST    Post subject: Re: main street dam Reply with quote

Do they have a date for the permanent fence yet?
Back to top
DCook-3q51
Guest





PostPosted: Wed, Dec 17 2014, 4:08 pm EST    Post subject: Re: main street dam Reply with quote

The Lake railing is being assembled now with the expected installation being the beginning of January.

Dave Cook
Township Committee
Back to top
AnonQqqqq-3n92
Guest





PostPosted: Sat, Dec 20 2014, 3:01 pm EST    Post subject: Re: main street dam Reply with quote

Looks great! What will the railing look like?